How to calculate OEE, with a worked example

OEE, overall equipment effectiveness, puts one number on how much of a machine's scheduled time turns into good parts. Here is the formula, an example worked line by line, and the mistakes that make the number look better than the machine.

OEE is the share of scheduled production time that turns into good parts at full speed. To calculate OEE, you multiply three factors: availability, performance and quality. Each one catches a different kind of loss, so the number tells you how much you’re losing and the factors tell you where. It works the same on a CNC machine, a packaging line or a robot cell.

In short

OEE = availability × performance × quality. Availability is run time divided by planned production time. Performance is ideal cycle time times total count, divided by run time. Quality is good count divided by total count. Multiplied together, they reduce to good count × ideal cycle time ÷ planned production time: the share of scheduled time spent making good parts at the fastest proven rate.

The OEE formula, factor by factor

The definitions below follow the widely used ones published by Vorne at oee.com. OEE also appears among the manufacturing KPIs defined in ISO 22400-2:2014, which is due for revision.

Factor Formula What it catches
Availability Run time ÷ planned production time Stops: breakdowns, changeovers, waiting for material
Performance (Ideal cycle time × total count) ÷ run time Running slower than the ideal, and short stops
Quality Good count ÷ total count Scrap and rework, counted first pass
OEE Availability × performance × quality All of the above

Two terms decide whether the number means anything:

  • Planned production time is the time the machine was scheduled to run. Breaks and shifts with no work scheduled come out. Changeovers stay in and count as stop time.
  • Ideal cycle time is the fastest the process can make one part under good conditions, such as the cycle proven at the run-off or the machine’s rated speed. It isn’t last month’s average.

OEE example, worked step by step

One cell, one eight-hour shift:

Item Value
Shift length 480 min
Break 30 min
Planned production time 450 min
Changeover 25 min
Fault stops 20 min
Run time 405 min
Ideal cycle time 30 s per part
Total count 720 parts
Rejects, including rework 18 parts
Good count 702 parts

Availability = 405 ÷ 450 = 90.0%. The cell was scheduled for 450 minutes and ran for 405.

Performance = (30 s × 720) ÷ (405 min × 60 s) = 21,600 ÷ 24,300 = 88.9%. At the ideal rate, 720 parts take 360 minutes. The cell took 405.

Quality = 702 ÷ 720 = 97.5%.

OEE = 0.900 × 0.889 × 0.975 = 78.0%.

As a check, good count × ideal cycle time ÷ planned production time = 702 × 30 s ÷ 27,000 s = 78.0%. Both routes give the same answer, but only the three factors show where the time went: 45 minutes lost to stops, 45 to running slow, and 9 to making parts that were rejected.

What is a good OEE?

The figure quoted most often is 85%, called world class. Vorne traces it to Seiichi Nakajima, who introduced OEE with Total Productive Maintenance in Japan, and it is usually broken down as about 90% availability, 95% performance and 99% or better quality.

Vorne also says that most manufacturers it works with score closer to 60%, and that it sees more plants below 45% than above 85%. Its advice is to set targets against your own process and keep raising them, rather than chasing an outside benchmark. A line that runs ten products and changes over all day won’t score like a line that runs one. That matches how we’d use the number: as a trend on one cell, not a grade.

The six big losses behind availability, performance and quality

Each factor breaks into two kinds of loss. These six categories come from the same Total Productive Maintenance work as OEE.

Factor Loss On a robot cell, for example
Availability Equipment failure (unplanned stops) A faulted gripper, a machine alarm, the cell starved of parts or blocked downstream
Availability Setup and adjustments (planned stops) Changing fingers and programs for the next part number
Performance Idling and minor stops Misfeeds, a part not seated, a quick reset by the operator
Performance Reduced speed The robot’s speed override left below 100% after someone stepped through a recovery
Quality Process defects Rejected parts in steady running
Quality Reduced yield Scrap while a changeover settles in

Minor stops are the ones most plants miss. Vorne notes they are usually short, cleared by the operator, and rarely tracked. On a clipboard, a two-minute stop repeated forty times a shift may never appear. In a time-stamped log it does.

OEE vs TEEP, and what an unmanned shift changes

OEE only looks at scheduled time. TEEP, total effective equipment performance, multiplies OEE by utilization, which is planned production time divided by all the time in the period.

In the example above, one 450-minute shift out of 1,440 minutes in a day is a utilization of 31%, so TEEP is 0.78 × 0.31 = 24%. Adding a second shift, or an unattended third, raises utilization and TEEP without touching OEE. Our guide to lights out manufacturing covers what a cell needs before it runs with nobody watching.

Common mistakes when calculating OEE

  • Ideal cycle time set too slow. Performance looks great and can pass 100%, which means the ideal was wrong.
  • Changeovers left out. Leaving changeovers out of availability hides one of the biggest losses, especially on high-mix work.
  • Rework counted as good. OEE quality is first pass. A part that had to be reworked isn’t a good part.
  • Averaging percentages. Averaging the OEE of a cell that ran two hours with one that ran twenty gives the short run the same weight. Add up the times and counts first, then calculate.
  • Comparing different processes. A press, a weld cell and a packaging line lose time in different ways. Compare each one with itself.

What a robot cell changes in each factor

Measure OEE on the manual process before you automate it, so the comparison afterwards is real. A robot moves the three factors in different ways, and not always up.

  • Availability usually rises where the machine used to sit idle waiting for an operator who was loading another machine, on a call or covering a gap in the crew. It can fall if the cell brings new stops of its own: gripper faults, misfeeds from a feeder or a part presented out of position.
  • Performance tends to steady, because the robot runs the same path at the same speed every cycle. Whether it rises depends on whether the operator or the machine was setting the pace.
  • Quality often improves where handling caused the defects, such as parts dropped, loaded crooked or marked by hand. It won’t fix a process that makes bad parts on its own.

Changeovers deserve their own look. If each part number needs new fingers and a new program, the time it takes to swap them lands in availability every time the job changes.

How to measure OEE on a robot cell

A robot cell already knows most of what OEE needs. The PLC sees every cycle, every reject signal, every fault and every time the cell waits for parts or for room downstream. Logged with a time stamp, those signals give availability, performance and quality without anyone writing on a clipboard. What the operator adds is the reason for a long stop, picked from a short list on the screen.

Operator touch screen showing last cycle time for tables A, B and C, a row of color changeover buttons, reject and total counters with a reset button, and five fault lights
Fig. 1The operator screen we wrote for the Temecula assembly cells: last cycle time for each table, color changeover, reject and total counts, and fault lights.

We build cells that log every cycle and fault, time-stamped and searchable, on a custom HMI written for the crew. The counts can post to your ERP without re-keying, which is covered under machine data and ERP integration. Our machine monitoring page covers status boards and push alerts to phones.

If you’re weighing a new cell, a measured OEE on the manual process is a better starting point than a guess. Run your figures through the robot ROI calculator, then send us the process and the numbers.

Common questions

What is the difference between OEE and TEEP?
OEE measures how well equipment runs during the time it is scheduled to run. TEEP, total effective equipment performance, multiplies OEE by utilization, which is the scheduled time divided by all the time in the period. A machine scheduled for one shift a day can have a high OEE and a low TEEP. Adding a shift, or running unattended overnight, raises utilization even if OEE stays the same.
Should planned maintenance and changeovers count against OEE?
In the common definition, changeovers count as stop time and lower availability, because the machine was scheduled to run and didn't. Time with no production scheduled, such as breaks or a shift with no work, is left out of planned production time. Some plants also leave out planned maintenance. Whichever rule you pick, write it down and keep it, or the trend will move when nothing on the floor changed.
Can OEE be over 100 percent?
No. If performance comes out above 100 percent, the ideal cycle time is set too long: the machine is beating a number that was never its best. Set the ideal cycle time to the fastest the process can really run, such as the cycle proven at the run-off or the machine's rated speed, not the average of last month.
How do you measure OEE on a robot cell?
Let the controls count. The PLC already knows when the cell is running, stopped, waiting for parts or blocked downstream, and it can count every cycle and every reject. Log those with time stamps and the three factors fall out of the data. Ask the operator only for what the controls can't know, such as the reason for a long stop.

Sources

  1. Vorne (oee.com): Calculate OEE, definitions and formulas
  2. Vorne (oee.com): World-class OEE, the 85% figure and its origin
  3. Vorne (oee.com): The six big losses
  4. Vorne (oee.com): Calculate TEEP
  5. ISO 22400-2:2014, Key performance indicators (KPIs) for manufacturing operations management, Part 2: Definitions and descriptions

Start a project

Bring us the process. We'll bring the cell.

Send a phone video of the manual process, or a part drawing, by text or email. We come back with a cell concept and a plan: robot, tooling, controls and code.

Call or text
Call or text
(818) 397-4809
Email
sales@calwestmfg.com
Shop
13815 Arrow Rte, Fontana, CA 92335
Hours
Mon–Fri 7:00am – 3:45pm

FANUC Authorized System Integrator (ASI). Part of CalWest Manufacturing, founded 2012: AS9100D and ISO 9001 certified, ITAR registered.