How a robot integration project works with us

Every stage from the first call to handover, and what we need from your side at each one.

FANUC weld robot on a custom base built in the CalWest shop
Fig. 1A FANUC robot on a base we designed and built in our Fontana shop.

Most of the robot integration project process happens on our side. At CalWest Robotics we model the cell, cut and weld the frame, wire the panel and write the code in one shop in Fontana, CA. Your part is smaller, but it decides how well the cell fits your line. At each stage we ask you for a few things, and at the run-off you see the cell work with your parts.

In short

A robot cell project with us starts with a video, drawing or description of your process. We come back with a concept and a plan, and a review of that concept with your team leads to a firm quote. Then we model the full cell in SolidWorks, fabricate, wire and program it in our Fontana shop, run it off there with your parts, install and commission it on your floor, and hand it over to your crew.

The stages at a glance

  1. Send us the process

    Call or text (818) 397-4809, or send a phone video of the job being done by hand, a part drawing, or both.

  2. Concept and plan

    We come back with a cell concept (robot, gripper, layout, how parts get in and out) and a plan, so you can tell early whether the project fits.

  3. Design review and firm quote

    We walk your team through the concept and settle the open questions, such as how parts are presented, where the operator stands and how the cell signals the machines on either side. Then we quote the cell as reviewed.

  4. Build in Fontana

    After the order, the full cell is modeled in SolidWorks. Then the frame, guarding, control panel, gripper and code are made in our shop by one team.

  5. Run-off (FAT)

    The finished cell runs your parts in our shop before it ships. You're invited to watch it and to push on it.

  6. Install and SAT

    We install and commission the cell on your floor, then run the site acceptance test with your crew and the equipment on either side of it.

  7. Handover

    Your operators and maintenance lead take the cell over. Settle which documents come with it before the PO.

  8. After install

    Support terms depend on the job. Agree on them before the PO, especially if your plant runs nights or weekends.

What should you send a robot integrator first?

The most useful first message is a short video of someone doing the job by hand. Phone footage is fine. We want to see the part, how it arrives at the station, what the operator does with it and where it goes next. A part drawing or CAD model covers most of the rest.

Plenty of plants don’t allow cameras on the floor. If yours is one of them, describe the station on a call or send a sketch: what comes in, what goes out, what the operator does in between, and how many per shift. That’s enough to start a concept.

What to send us (whatever you have)

  1. A video of the manual process, or a description if you can't film
  2. Part drawings or CAD models, and sample parts, including the ugly ones
  3. The rate you need, in parts per minute or per shift, and how many shifts you run
  4. How many part numbers or variants run through the station, and how often you change over
  5. Floor space: a dimensioned sketch with ceiling height, columns, forklift aisles and slab thickness if you know it
  6. Utilities at the spot: voltage and phase, compressed air, network drops
  7. Your plant's PLC and HMI standard, if there is one (Allen-Bradley, Siemens or another)
  8. Safety and insurance requirements your EHS team or insurer applies to new machinery
  9. Any machine specs or vendor standards your plant hands to suppliers

You don’t need all of it to start. A video or a drawing is enough for a concept, and the rest firms up the quote. If you’d rather fill the list in and print it, the automation RFQ builder turns these into one project brief.

Email files to sales@calwestmfg.com or text them to (818) 397-4809. The contact page can start that email for you.

Drawings under ITAR or export control

CalWest Manufacturing, our parent company, is ITAR registered. That doesn’t make ordinary email or a text message a controlled channel, so please don’t send controlled drawings either way. Call us at (818) 397-4809 before sending anything controlled. A first concept can often start from what your export-control officer is willing to release, such as the part’s overall size, weight, material and grip points.

From concept to firm quote

The concept is a layout, not a finished design. It shows which FANUC robot we’d use, what the gripper does, where parts come in and leave, where the guarding goes and where the operator stands. It comes with a plan, so you can decide early whether to keep going.

If you want a rough sense of cost first, the robot cell cost breakdown lists what goes into a cell, and the robot ROI calculator works out payback from your own labor and volume figures.

The design review is where the cell gets settled. We walk your engineering, maintenance and production people through the concept and work through the open questions, from how parts are presented to where the operator stands. This is the cheapest point to change your mind. Moving a conveyor on the layout takes an edit. Once the frame is welded, it means cutting new steel.

Bring the people who will live with the cell to this review. Operators notice where a bin will be awkward to swap. Maintenance notices where a motor can’t be reached without pulling a guard panel. The firm quote then covers the cell as reviewed.

Built in one shop in Fontana

Once the order is in, the cell goes through our five steps: design, fabricate, wire, code and install. The full cell is modeled in SolidWorks, and reach and clearances are proven there before any steel is cut. Frames and guarding are laser-cut, bent and welded here. Control panels are built, wired and tested here, grippers are machined on our 5-axis, and the robot and PLC programs are written by the same team that builds the cell. The robots are all FANUC: LR Mate arms, delta robots, and larger six-axis arms like the ones on our palletizing cells. The robot cell design and build page goes through each step. For each part of a cell and who makes it, see what a turnkey cell includes.

For you, this stretch is mostly quiet. Expect questions from us as the build turns up details the model didn’t settle, such as the signal handshake with your upstream machine or which way a label has to face.

Open control panel with an Allen-Bradley CompactLogix PLC, rows of red safety relay modules and labeled wiring run in white duct
Fig. 2A cell control panel, built, wired and tested in our shop.
Machined aluminum gripper fingers holding a white molded clip above an orange plastic part on an assembly fixture
Fig. 3Gripper fingers machined in-house to fit the part they carry.

What happens at the run-off (FAT)?

The factory acceptance test is the run-off in our shop, before the cell ships. The cell runs your parts at the rate in the spec, through the cases that matter on a real shift: normal production, each changeover, a jam, a missed pick, an empty feeder, and every guard door, light curtain and E-stop. A pass is judged against the criteria agreed before the build started.

You’re invited. Bring the operator lead and the maintenance tech who will own the cell. They will learn more from an afternoon of watching it fault and recover than from a binder, and any change they ask for is quickest to make here, where the frame, the panel, the gripper and the code are all under one roof. If the gripper fingers mark the part or let it shift, new ones are machined on our own 5-axis and fitted the same week.

Send production parts for the run-off, and send enough to run the cell for a while. Include the ugly ones: the burr, the crushed corner, the batch that came in slightly off. Those are the parts that cause misses and jams on your floor, so they belong in the run-off. The FAT and SAT guide lists what belongs on each test sheet.

Install and SAT on your floor

We install and commission the cell on your floor, and our service area covers plants across the US. Before we arrive, a few things are usually on your side of the list: power and air run to the spot, a floor that can take the anchor bolts (slab thickness matters for the robot base), network access if the cell reports to your systems, and a window when the line can be down.

The site acceptance test then repeats the key checks from the run-off with your utilities, your upstream and downstream equipment and your crew alongside ours. When it passes, your crew takes the cell over. The projects page shows cells built this way, among them palletizing cells and robot assembly cells designed and built in Fontana and commissioned on a live production floor.

Guarded LR Mate robot assembly table running on a customer's production floor, controller and teach pendant mounted below the enclosure
Fig. 4One of three LR Mate assembly tables, commissioned on a customer's production floor.
Yellow FANUC robot inside green guarding at the end of a packaging line, with finished cases standing on the pallet beside it
Fig. 5A palletizing cell at the end of a packaging line, running on the customer's floor after install.

How long does a robot cell project take?

We don’t publish typical durations, because a range wide enough to cover every cell tells you little about yours. A robot cell project timeline mostly comes down to these:

  • Lead time on the robot and other bought parts: FANUC arms and controllers, safety devices, conveyors, cameras.
  • How quickly the design review closes. Every round of layout changes pushes back the start of fabrication.
  • When production parts are available for gripper development and the run-off.
  • How hard the part is to hold. A part that marks, flexes or tangles can take more than one round of fingers.
  • Your install window: a planned shutdown, a long weekend, or a line that can’t stop at all.
  • Site readiness on install day: power, air, anchoring and network.

The plan we send with the concept is where your schedule starts. Dates firm up once the design review closes and the long-lead parts are ordered. Our guide to the phases of a robot integration project covers what each one waits on.

What to settle before the PO

Some details are easy to leave vague until the cell is on your floor. Ask us about each of these when we quote, and ask every integrator you’re comparing the same questions. Our guide on how to choose a robot integrator has more of them.

Get these in writing

  1. The handover documents, by name: electrical schematics, bill of materials, spare-parts list, robot and PLC backups, operator and maintenance instructions
  2. Whether you receive the robot, PLC and HMI source code, and whether any of it is locked
  3. How warranty is split between the FANUC robot and the rest of the cell
  4. Who you call when the cell faults, and what happens outside the integrator's hours
  5. Payment milestones and what triggers each one
  6. What counts as passing the FAT and the SAT
  7. What training is included, and for which of your operators and maintenance staff

Our hours are Mon–Fri 7:00am – 3:45pm. If your plant runs nights or weekends, tell us early, so support is agreed up front rather than assumed. If purchasing needs vendor paperwork before a PO, send that list with your first request so it runs alongside the quote instead of holding up the order.

Start a project

Bring us the process. We'll bring the cell.

Send a phone video of the manual process, or a part drawing, by text or email. We come back with a cell concept and a plan: robot, tooling, controls and code.

Call or text
Call or text
(818) 397-4809
Email
sales@calwestmfg.com
Shop
13815 Arrow Rte, Fontana, CA 92335
Hours
Mon–Fri 7:00am – 3:45pm

FANUC Authorized System Integrator (ASI). Part of CalWest Manufacturing, founded 2012: AS9100D and ISO 9001 certified, ITAR registered.