CalWest ManufacturingRobotics Fontana, CA

Call or text (818) 397-4809

Robot ROI and payback calculator

Put in your own shifts, labor cost and cell quote to see annual savings, simple payback, and ROI after three and five years. It is pre-tax, every formula is written out below the form, and nothing you type leaves your browser.

The numbers already filled in are examples to show how the math works. Replace each one with yours. The cell cost is blank on purpose: use the quote you have.

When the cell runs
shifts Example: 2. One to three.
hours Example: 8. Paid hours the job is staffed today.
days Example: 250, five days a week for 50 weeks.
Labor
people Example: 1. Count a person only if their cost really goes away or moves to work you would otherwise pay for.
$ per hour Example: $48.62, the U.S. average total compensation per hour in private manufacturing (BLS, June 2026). Wage plus benefits; your own number may be higher or lower.
The cell
$ Your quote, plus freight, rigging, utility hookups and training. See the robot cell cost breakdown.
% a year Example: 3%. A placeholder for the arithmetic, not a benchmark. Spare parts, service and the time of whoever looks after the cell.
% Example: 90%. The share of staffed hours the cell does the work. When it is down, assume a person does it.
Other savings (optional)
$ a year Scrap and rework you expect the cell to remove, from your own records.
$ a year Only what is not already counted in the operators above.
$ a year Extra units a year you can sell, times the margin on each unit.
% a year Example: 8%. Use your finance team's rate.

Result

Enter your cell's installed cost to see payback.
Your numbers, per year unless noted
Labor hours the cell takes over–
Labor savings–
Scrap, overtime and throughput–
Maintenance–
Net savings–
Simple payback–
ROI after 3 years–
ROI after 5 years–
NPV over 5 years–
Payback in months, by labor cost and shifts
Labor cost1 shift2 shifts3 shifts
25% lower–––
As entered–––
25% higher–––

Pre-tax. No financing cost, no wage growth, and the same savings every year. Your current case is in bold.

The link keeps your numbers after the # in the address, which is not sent to our server. The send link opens an email in your own mail program; nothing is sent until you press send. Example labor cost: BLS Employer Costs for Employee Compensation, June 2026, Table 4.

How the numbers are worked out

The calculator does simple arithmetic you can check by hand. It counts the labor hours the cell takes over, prices them at your labor cost, adds any other savings you entered, and takes off maintenance. That net figure, set against the installed cost, gives payback and ROI.

The formulas
Labor hours a yearoperators per shift × hours per shift × shifts per day × days per year × uptime
Labor savingslabor hours a year × labor cost per hour
Maintenancecell installed cost × maintenance %
Net savingslabor savings + scrap and rework + overtime and temp + throughput gain − maintenance
Simple paybackcell installed cost ÷ net savings × 12, in months
ROI after N years(net savings × N − cell installed cost) ÷ cell installed cost
NPV over 5 yearsnet savings ÷ (1 + r) + net savings ÷ (1 + r)² + … + net savings ÷ (1 + r)⁵ − cell installed cost, where r is the discount rate

With the example inputs, one operator on each of two 8-hour shifts, 250 days a year at 90% uptime, is 3,600 labor hours a year. At $48.62 an hour that is $175,032 a year in labor savings. Add any other savings, take off a year of maintenance, and divide your installed cost by what is left. Times 12, that is the payback in months.

What is counted, and what is left out

Counted: labor hours the cell takes over, scrap and rework, overtime and temp labor, extra output you can sell, and yearly maintenance. Each is a cash figure you should be able to point to in your own books.

Left out, because each one depends on your business or your tax position:

  • Taxes and depreciation, including Section 179 and bonus depreciation.
  • Financing cost, if you borrow or lease.
  • Wage increases over the years, which would shorten payback.
  • Ramp-up: the weeks after install when the crew is learning the cell and output is below plan.
  • Injury and workers' comp exposure, floor space and quality claims, which are real but hard to price.
  • What the cell is worth when you are done with it.

Why robot payback varies so much

Labor savings grow in a straight line with shifts and with labor cost, while the cell costs the same whether it runs one shift or three. A cell that replaces one person on one shift has to pay for itself from about 2,000 hours a year. The same cell on three shifts has three times the hours to do it. That is why an end-of-line job such as a robotic palletizing cell that runs every shift the line runs tends to pay back faster than a cell that works a few hours a day.

The payback table with the result shows this for your inputs. Each row moves the labor cost 25% down or up, and each column changes the number of shifts, with everything else held as you entered it.

The other big swing is whether the labor cost really goes away. If the operator moves to another job you were going to hire for, the saving is real. If they stay in the same place watching the robot, it is not. Uptime matters for the same reason: when the cell is down, someone does the work by hand.

What goes into the cell cost

Use the installed cost, not the robot price. A cell is the robot, the gripper, guarding, controls, programming, install and training. The robot cell cost breakdown goes through each line. We don't publish prices, because what a cell costs depends on the part and the process. If you don't have a quote yet, how we work explains what we need from you to give you one.

Taxes are not in this number

The result is before tax. Federal first-year write-offs can shorten the after-tax payback on a robot cell, and California does not follow the federal rules for them. Our guide to Section 179 and a robot cell covers the federal side, and California incentives for robot cells covers the state's partial sales tax exemption and other programs. Neither this page nor those guides is tax advice. Ask your CPA to work out the after-tax figure for your business.

Sharing and sending your numbers

The address in your browser updates as you type, so you can copy it into an email or a capex request and the other person sees the same numbers. "Send these numbers to CalWest" opens a new email to sales@calwestmfg.com in your mail program with your inputs and results written out. You can edit it or delete it before sending. For more on planning a first cell, see automation for small manufacturers, or go straight to the contact page.

Common questions

How do I calculate payback on a robot cell?
Divide the installed cost of the cell by what it saves each year after its running costs, then multiply by 12 to get months. Labor usually leads the savings: people per shift, times hours, shifts and days a year, times what an hour of that labor really costs you. Add scrap, overtime and throughput gains you can back up, subtract maintenance, and you have the net figure this calculator uses.
What should count as savings?
Only costs that actually go away, or work you would otherwise have to pay for. Labor counts when headcount, overtime or temp hours really drop, or when the people move to work you would have hired for. Scrap and rework count if you have the numbers. Extra throughput counts only if you can sell the extra output. Floor space and injury risk are real but hard to price, so they are left out here.
Does this calculator include tax effects?
No. The result is pre-tax. Federal first-year write-offs such as Section 179 and bonus depreciation can shorten the after-tax payback, and California follows different rules for both. Our guides to Section 179 for a robot cell and to California incentives explain how each one works, but your CPA should run the numbers for your business before you count on them.
Why use a fully-loaded labor cost instead of the hourly wage?
Because the wage is not what an hour of labor costs you. Benefits, payroll taxes and insurance sit on top of it. The example rate is the Bureau of Labor Statistics figure for total compensation per hour in private manufacturing, which includes benefits but not your own overhead. Your payroll or finance team can give you the real number for the job the cell would do.
Are the numbers I type sent anywhere?
No. The math runs in your browser. The share link keeps your numbers in the part of the address after the # sign, which browsers do not send to the web server. The send link only opens a new email in your own mail program, and nothing goes out until you press send yourself.

Sources

  1. U.S. Bureau of Labor Statistics: Employer Costs for Employee Compensation, June 2026, Table 4 (private industry workers by occupational and industry group)

Start a project

Bring us the process. We'll bring the cell.

Send a phone video of the manual process, or a part drawing, by text or email. We come back with a cell concept and a plan: robot, tooling, controls and code.

Call or text
Call or text
(818) 397-4809
Email
sales@calwestmfg.com
Shop
13815 Arrow Rte, Fontana, CA 92335
Hours
Mon–Fri 7:00am – 3:45pm

FANUC Authorized System Integrator (ASI). Part of CalWest Manufacturing, founded 2012: AS9100D and ISO 9001 certified, ITAR registered.