Relocating an industrial robot: moving a FANUC robot and its cell
What has to happen before, during and after a FANUC robot moves to a new spot on the floor or to another plant, so it comes back up knowing where it is and the cell around it is still safe.
Relocating an industrial robot is mostly about what happens either side of the lift. A FANUC robot that is backed up, parked in its transport pose and moved with good batteries comes back up knowing where its axes are. One that isn’t can arrive with lost counts, a cracked cover from a short sling, or programs that miss every fixture by the distance it moved. This guide covers a FANUC robot moving to a new spot on the same floor or to another plant: the backups, the transport pose, the batteries, anchoring at the new spot, the mastering check, re-teaching and the new risk assessment. The figures quoted come from FANUC’s manuals for the LR Mate 200iD, M-20iD and M-710iC. Use the manual for your exact model.
In short
Before the move
Do these while the robot still runs where it is
- Take an All of above backup and an image backup, and copy both off the robot
- Write down the mastering data and run the robot to its reference check points, so you have something to compare against later
- Record which programs use which user frames, and where each fixture sits relative to the robot base
- Photograph the cable and hose routing, the controller connections and the dress pack
- Record the Dual Check Safety settings, if the robot has them
- Check the age of the pulsecoder batteries in the arm
Our FANUC robot backup guide covers the two backup types, and the mastering guide explains how to set up reference check points that make the check after the move quick.
Keep the pulsecoder counts
While the controller is off, batteries hold each pulsecoder’s position count. If they go flat, or the circuit between them and the pulsecoders is broken, the robot wakes up with SRVO-062 BZAL and has to be mastered before it does anything else.
Find where your robot’s batteries are before anything is unplugged. On the M-20iD they sit in the J1 base. The LR Mate 200iD can have them built in, or in an external battery box that FANUC’s manual says can be built into the controller or another unit, so trace that cable first. If the batteries are near their replacement interval, change them before the move, with the controller powered on and the e-stop pressed, as FANUC’s procedure requires. Our BZAL guide covers the alarm if it appears anyway.
Transport pose and lifting
Each mechanical unit manual has a transport drawing: the pose, the robot’s mass, the lifting points, the sling and eyebolt ratings and the optional forklift brackets. Three examples:
| Model | Transport pose (J1 to J6, degrees) | Mass | Lifting |
|---|---|---|---|
| LR Mate 200iD (standard) | 0, -30, -40, 0, -45, 0 | 25 kg | Transport equipment on the base, four slings with shackles |
| M-20iD/25 | 0, -25, -47, 0, -55, 0 | 250 kg | Two M10 eyebolts, two crossed slings, or FANUC’s forklift brackets |
| M-710iC/20L | -10, -25, -55.5, 0, -34.5, 0 | 540 kg | Four M16 eyebolts and four slings, or FANUC’s forklift equipment |
Move the robot into the pose under power before shutdown. A short program with the pose in it, stepped in T1, makes that repeatable.
FANUC’s warnings in these manuals are worth reading as a list. Take the end effector off, because the robot becomes unstable with it on. If it can’t come off, the M-710iC manual shows the arm blocked with wood so vibration can’t swing the tool and shock-load the reducers. Use the forklift pockets only for transport, never to secure the robot. Check the bolts on the transport equipment before lifting, don’t pull eyebolts sideways, keep slings off the motors, connectors and cables, and set the robot down slowly so its mounting surface doesn’t strike the floor. On the LR Mate, the manual warns that slings that are too short can break the J2 base or the J2 arm cover.
The lift belongs to a qualified rigger working from FANUC’s drawing for your model. Disconnect the robot and controller cables with the power off and locked out. If the robot has to sit before it is installed, FANUC says to store it on a level surface in the transport pose. The R-30iB Mate controller is lifted by the eyebolts on its top.
Anchoring at the new spot
All three manuals set the same limits for the mounting surface: flatness within 0.5 mm and inclination within 0.5 degrees, or the base can break and the robot can perform poorly. The M-20iD manual’s example installation fixes a floor plate with four M20 chemical anchors and bolts the robot to it with four M16 x 40 bolts at 318 Nm, and it says not to level the robot base directly with push bolts or wedges. Anchor strength depends on the concrete, so follow the anchor maker’s guideline.
The manuals also tabulate the force and moment on the base during a power-off stop, and those are the numbers a base or riser has to be designed for. Our parent company, CalWest Manufacturing, makes bases, risers and guarding in the same Fontana building where we build our cells.
Two more items from the manuals. Leave room in front of the base for the mastering fixture. And if the robot used to be floor-mounted and is now on a wall or inverted, set the new mount angle at a controlled start under MENU, MAINTENANCE.
For the controller, the R-30iB Mate manual’s checks at installation run in order: check inside and outside the cabinet, terminals and connectors, connect the robot cables, connect input power with the breaker off and check the voltage, power on with the e-stop pressed, check the robot interface signals and parameters, release the e-stop, jog each axis, then check the end effector and peripheral signals.
Mastering check after the move
If the batteries held, the robot should still be mastered. Prove it before trusting it: run to the reference check points in T1 at low speed and put the axes at zero against the witness marks. If anything disagrees, master that axis again rather than touching up points. FANUC notes that quick mastering using the power-off position can’t be used after a robot is installed or moved.
Re-teach or shift the programs
Taught points are stored relative to the robot. If the robot and its fixtures moved together on one base, they may still line up. Check them. If not:
- Points in user frames. Re-teach each frame on its fixture at the new spot, and the points follow it. Our user frame setup guide covers the methods.
- Points in world coordinates or joint angles. FANUC’s Program Shift utility, under MENU, UTILITIES, can move a program’s points by a shift found from three source and three destination points. Its rules matter: position data in position registers isn’t converted, and joint data stays joint data.
- Vision. A camera that moved, or whose target moved, needs its calibration redone. Our iRVision calibration guide covers it.
Then step every program through in T1 at low speed before AUTO. That is how we run any new motion on the floor.
A new risk assessment at the new spot
A cell in a new place has new hazards: different access, different traffic, different distances to aisles and other machines. ISO 10218-2:2025 sets safety requirements for robot applications and cells, including risk assessment, and the US adopts it as part of ANSI/A3 R15.06-2025. The stopping times and distances in FANUC’s manuals are reference values, and the M-20iD manual says to measure the actual ones. Any DCS zones or limits have to be checked against the new layout. Our guides to robot risk assessment and robot cell guarding cover both, and your own safety professional should review the result.
Take a fresh backup once the robot runs at the new spot, and label it as the new baseline.
Moving a robot or rebuilding the cell around it is part of our FANUC robot service work, on robots we didn’t build as well as our own: backups, the mastering check, frames and points, and new guarding made in Fontana. Call or text (818) 397-4809 with the robot model and where it is going.
Common questions
- Does a FANUC robot need to be remastered after it is moved?
- Not if the pulsecoders kept their counts. The backup batteries hold each axis's position while the robot is unpowered, so a robot moved with good batteries and its cables intact should come back up mastered. Check it anyway against reference points and the zero witness marks. If it powers up with SRVO-062 BZAL, it has to be mastered, and FANUC says quick mastering using the power-off position isn't valid after a robot is moved.
- Will my FANUC programs still work after moving the robot?
- The programs move with the controller, but taught points are stored relative to the robot. If the fixtures and conveyors end up in a different place relative to the arm, the points miss. Points taught in user frames can be recovered by re-teaching the frames. Points in world coordinates can be moved with FANUC's shift utilities, which don't convert position registers, or touched up one by one.
- What position should a FANUC robot be in for shipping?
- The transport pose drawn in the mechanical unit manual for that exact model. For example, FANUC gives J1 0, J2 -25, J3 -47, J4 0, J5 -55 and J6 0 degrees for an M-20iD/25, and J2 -30, J3 -40 and J5 -45 degrees with the other axes at 0 for a standard LR Mate 200iD. The manual also shows the lifting points, the slings and the transport equipment.
- Can I move a FANUC robot with the end effector on?
- FANUC's manuals say to take it off. The robot becomes unstable with the tool on, and vibration in transport lets the tool swing and shock-load the reducers. The M-20iD manual allows light items such as a welding torch to stay. Where a tool can't come off, the M-710iC manual shows the arm blocked with wood so the tool can't move.
- Do we need a new risk assessment after relocating a robot cell?
- Yes. The stopping distances, the guarding, the access points and the people working nearby are all different at the new spot. ISO 10218-2:2025 sets requirements for robot applications and cells, including risk assessment, and the US adopts it in ANSI/A3 R15.06-2025. Check any Dual Check Safety zones against the new layout too, and have your own safety professional review the result.
Sources
- FANUC ARC Mate 120iD / M-20iD mechanical unit operator's manual, B-84074EN/03: 1 Transportation and installation (hosted by Haas Automation)
- FANUC LR Mate 200iD / ARC Mate 50iD mechanical unit operator's manual, B-83494EN/06: 1 Transportation and installation, 7.3.1 batteries (hosted by Haas Automation)
- FANUC M-710iC/20L/12L/20M mechanical unit operator's manual, B-82514EN/09: 1 Transportation and installation, 7.4 Storage (hosted by Haas Automation)
- FANUC R-30iB Mate/R-30iB Mate Plus controller maintenance manual, B-83525EN/07: 5 Transportation and installation (hosted by Haas Automation)
- FANUC America: Robot support and manuals (R-30iB/R-30iB Plus Operator's Manual Basic Function B-83284EN/12: 9.2 Shift functions, 9.3 Coordinate system change shift functions, B.2 Mastering; via the Customer Resource Center)
- FANUC Tech Transfer: How to replace batteries on an industrial robot (battery location on the M-20iD, power stays on)
- FANUC Tech Transfer: Quick mastering on R-30iB Plus using power off position
- ISO 10218-2:2025, Robotics: safety requirements, Part 2: Industrial robot applications and robot cells
- A3: New ANSI/A3 R15.06-2025 American National Standard for industrial robot safety now available
- OSHA 29 CFR 1910.147: The control of hazardous energy (lockout/tagout)