Robot risk assessment: a task-based method, step by step

The guarding, the safety devices and the procedures on a robot cell should all trace back to one document: the risk assessment. This guide walks through how a task-based assessment is done and what it should contain when it reaches your plant.

A robot risk assessment lists every task people perform at a robot cell, finds what can hurt them during each one, rates the risk and records how it is reduced. The guarding you see on a cell should be the result of that document, not a catalog choice. We build FANUC cells and do a risk assessment on each one. We are not a safety consultancy, so read this as background for a conversation with your own safety professional.

In short

A task-based robot risk assessment sets the limits of the cell, lists every task people do there, identifies the hazards of each task and rates the risk by severity, exposure and the chance of avoiding harm. It then reduces each risk in a fixed order: design it out, then guard it, then warn and train. Each task is rated again with the measures in place, and the team signs off what remains.

Which standards cover a robot risk assessment?

Several documents fit together. The robot standard tells you an assessment is needed. The general machinery standards say how to do one, and a technical report gives a robot-specific method.

Document What it is Status as of November 2026
ISO 12100:2010 The international method for risk assessment and risk reduction in machine design Current, last confirmed in 2022. A draft revision, ISO/DIS 12100.3, is in development to replace it
ANSI B11.0-2023 The US general machinery safety standard Current. ANSI notes it includes requirements for both suppliers and users of machinery, where ISO 12100 applies to suppliers
ANSI/A3 R15.06-2025 The US robot safety standard. Parts 1 and 2 adopt ISO 10218-1 and 10218-2:2025; Part 3 covers the plants that use robot cells Current. It replaced ANSI/RIA R15.06-2012
RIA TR R15.306-2016 A technical report describing a task-based risk assessment method for robot systems Still sold by A3, which describes it as one method that meets the 2012 edition’s requirement

OSHA has no robot-specific standard. Its technical manual chapter on industrial robots includes an example risk assessment based on TR R15.306, and it is free to read. Our robot safety standards guide covers what changed in the 2025 editions.

Who does the robot cell risk assessment?

OSHA’s technical manual says the integrator is responsible for making sure the assessment is completed and documented before commissioning, and for giving the results to the employer. It recommends including the workers who will run and maintain the cell, and says the employer should have the integrator train employees on the assessment before commissioning.

In practice the best assessments come from a small team: the integrator who knows the machine, the operators and maintenance techs who know the job, and the plant’s safety lead. The manual suggests a leader who knows the process, the robot application and the method, and a written result that each member signs.

Step 1: set the limits of the cell

An ISO 12100 risk assessment starts before any hazard is listed. Define what the cell is for, which parts it runs, at what speeds, and who will be near it. Include reasonably foreseeable misuse, such as an operator reaching in to straighten a part or someone propping a door open to save a step.

Define the spaces too. OSHA’s technical manual separates the robot’s maximum space, everything it could reach with gripper and part, from the restricted space it is limited to by limiting devices such as hard stops or safety-rated soft limits. Our guide to robot cell layout covers how those spaces shape the floor plan.

Step 2: list every task

A task-based risk assessment is organized around what people do, not around the machine’s parts. The list covers the cell’s whole life: installation, commissioning, normal running, changeover, teaching, cleaning, troubleshooting and maintenance, plus people who only walk past.

The manual’s own example adds a task most teams miss: changing the overhead lights above the cell. If someone does it, it goes on the list.

Step 3: identify the hazards of each task

For each task, list what can hurt the person doing it. OSHA’s example groups hazards like this:

  • Mechanical: crushing, caught-between, struck-by, shearing, cutting, projectiles.
  • Electrical: shock, arc flash, static.
  • Thermal: hot or cold surfaces and parts.
  • Ergonomic: reach, weight, posture, motion.
  • Slips, trips and falls: parts, hoses and coolant on the floor.
  • Machine instability: falling equipment or tools.
  • Environmental: fumes, dust, noise, light, sparks.

The gripper and the part belong here. Ask what happens to a held part when air or power is cut: a vacuum cup may drop it, and fingers may open. Stored energy in air lines, springs and gravity-loaded axes counts too.

Step 4: estimate the risk

ISO 12100 builds risk from the severity of possible harm and the probability of it happening. TR R15.306 turns that into three factors for each task and hazard:

  • Severity: how bad the injury could be.
  • Exposure: how often and how long the person is in the hazard zone, and whether the task is routine.
  • Avoidance: whether the person could sense the hazard and get out of the way.

A table in the report combines the three into a risk level, and the risk level sets the required performance level (PLr) for the safety functions that will protect that task. We won’t reproduce the report’s tables here. Buy the report, or read the example in OSHA’s technical manual, which reprints them.

Step 5: reduce the risk in the right order

ISO 12100 sets a three-step order:

  1. Inherently safe design

    Remove the hazard or shrink it by design. Move the load point outside the robot's reach, lower a speed or a force, or use a gripper that holds the part when air is lost.

  2. Safeguarding and complementary measures

    Fixed guards, interlocked doors, light curtains, scanners and limiting devices such as FANUC DCS position check, plus complementary measures such as emergency stops and a way to release a trapped person.

  3. Information for use

    Signs, warning lights, procedures and training for the risk that remains.

The order matters. The example in OSHA’s technical manual says that for tasks rated medium or higher, design or safeguarding should be the primary measure, not warnings or training. A sign never stands in for a guard. Our robot cell guarding page shows how we build the second step, and light curtain vs area scanner covers choosing between the two main presence-sensing devices. For limiting the robot’s travel in software, see our guide to FANUC DCS.

One task worked through, hypothetical

Take “clear a misfeed inside the cell” from the example list. The hazards: the arm restarting while a hand is in the fixture, a pinch between gripper and fixture, a cut from a sharp part edge, and a held part dropping when air is cut. Working down the order:

Step Measure for this task
Design Move the feeder pickup so most jams can be cleared from outside the guarding
Safeguarding An interlocked door that stops the robot and holds it stopped, with the reset outside and the fixture in view
Complementary Isolation of robot power and gripper air, with the held part set down first, for jams that need more than a quick reach
Information and PPE A written jam-clearing procedure, training, and cut-resistant gloves

Then the task is rated again with those in place.

Step 6: check the safety functions and what is left

Each safety function then gets a performance level it actually achieves, worked out under ISO 13849-1:2023 from how it is built: the devices, the wiring and the safety controller. Compare it with the PLr from step 4. If it falls short, change the design and check again. OSHA’s example calls this an iterative process, and it usually is.

Then rate each task again with the measures in place and record the residual risk. The team reviews it, agrees that it is acceptable, and signs.

What the risk assessment document should contain

Ask for these with the cell

  1. The limits of the cell: intended use, parts, speeds and foreseeable misuse
  2. The task list, including maintenance, cleaning and changeover
  3. The hazards found for each task
  4. The initial risk rating for each task and hazard
  5. The measures chosen, in order of the hierarchy
  6. The required and achieved performance level for each safety function
  7. The residual risk, and who accepted it
  8. The standard editions and method used, with a revision date

OSHA’s manual adds two points. The validated assessment should be given to everyone affected, and nobody should start a hazardous task until it has been issued and they have been trained on it. Keep the document. It is where the next change starts.

Keeping the assessment current

A new part, a new gripper, a faster speed, a moved conveyor or a new maintenance job all change the tasks or the hazards. The assessment should change with them. OSHA’s manual also expects periodic validation: checking the drawings, the safety function settings and the sensors against the document, not just walking past the fence. Part 3 of ANSI/A3 R15.06-2025 now covers the plant’s side of managing changes to a cell.

How we handle it on the cells we build

We do a risk assessment on every cell and lay out the guarding from it. The cell is modeled in SolidWorks, robot paths are checked in FANUC ROBOGUIDE before they run, and new motion is first stepped through slowly in T1 on the floor. We write the safety PLC logic in-house, on Allen-Bradley GuardLogix or Siemens, so the team that writes the safety functions works straight from the assessment.

Yellow FANUC LR Mate robot inside a black-framed enclosure with clear guard panels and a yellow Table B sign, on a factory floor
Fig. 1Table B of the three LR Mate assembly tables we built for a national lawn and garden brand in Temecula, CA. Each table is guarded, interlocked and light-curtained.

The run-off in our Fontana shop is the best time for your safety lead to test every door, curtain, e-stop and reset against the assessment, while changes are still easy. Our FAT and SAT guide covers what to test there. If you’re planning a cell, send us the process and a list of everyone who will work at it.

Common questions

Who is responsible for the robot cell risk assessment, the integrator or the plant?
Both have a part. OSHA's technical manual on robots says the integrator is responsible for making sure a risk assessment is completed and documented before commissioning and for giving the results to the employer, and it recommends involving the workers who will run the cell. The employer remains responsible under OSHA for a safe workplace, and the 2025 US robot standard added a part written for the plants that use robot cells.
Is RIA TR R15.306 a standard?
No. It is a technical report that describes one method of task-based risk assessment. A3 sells the 2016 version and describes it as a method that meets the risk assessment requirement of the 2012 edition of R15.06. The standard itself was reissued in 2025, so ask whoever does your assessment which method they use and how it maps to the edition the cell is designed to.
Do identical robot cells need separate risk assessments?
OSHA's technical manual says similar applications in the same plant should each have their own assessment. Two cells built from the same drawings can run different parts, different paths or different grippers, and one may sit next to a walkway while the other sits against a wall. The tasks and hazards can be copied as a starting point, but each cell should be checked where it actually stands.
How long does a robot risk assessment take?
It depends on the size of the cell and how many tasks people perform there. A table-top cell with one operator task is a short exercise. A cell with several load stations, frequent changeovers and maintenance inside the guarding takes longer. Most of the time goes into listing tasks with the people who do them, which is time well spent, because a missing task is a hazard nobody planned for.
When should a robot risk assessment be redone?
Whenever the cell or the way people work at it changes: a new part, a new gripper, faster speeds, a moved conveyor, an added station, a new maintenance task, or after an incident or near miss. OSHA's technical manual says the documentation should be kept and reviewed if any changes are made to the robot application, and that assessments should be reviewed and validated once the safeguards are in place.

Sources

  1. ISO 12100:2010, Safety of machinery: General principles for design, risk assessment and risk reduction
  2. ISO/DIS 12100.3, draft revision that will replace ISO 12100:2010, ISO/TR 22100-1 and ISO/TR 22100-2
  3. CEN-CENELEC: EN ISO 12100 and its relation to the Machinery Directive (presentation by the chair of ISO/TC 199)
  4. ANSI Webstore: ANSI B11.0-2023, Safety of machinery
  5. ANSI Blog: ANSI B11.0-2023 and its relationship to ISO 12100
  6. A3: New ANSI/A3 R15.06-2025 American National Standard for industrial robot safety now available
  7. ISO 10218-2:2025, Robotics, safety requirements, Part 2: Industrial robot applications and robot cells
  8. A3 Store: RIA TR R15.306-2016, Task-based risk assessment methodology
  9. OSHA Technical Manual, Section IV Chapter 4: Industrial robots and robot system safety, including Appendix 2, Example risk assessment
  10. ISO 13849-1:2023, Safety-related parts of control systems, Part 1: General principles for design

Start a project

Bring us the process. We'll bring the cell.

Send a phone video of the manual process, or a part drawing, by text or email. We come back with a cell concept and a plan: robot, tooling, controls and code.

Call or text
Call or text
(818) 397-4809
Email
sales@calwestmfg.com
Shop
13815 Arrow Rte, Fontana, CA 92335
Hours
Mon–Fri 7:00am – 3:45pm

FANUC Authorized System Integrator (ASI). Part of CalWest Manufacturing, founded 2012: AS9100D and ISO 9001 certified, ITAR registered.