How to automate a manufacturing process, step by step
The order we'd work through it in, from choosing the first process to supporting the cell after install, and what to have ready at each step.
Plants that automate a step well tend to do it in the same order. They choose the process carefully, write down how it really runs, prove the hard parts before buying, and plan for who will own the equipment. This guide on how to automate a manufacturing process follows that order, from the first candidate to support after install. We build FANUC robot cells in Fontana, CA and install them across the US, so the examples lean toward robots, but the steps apply to any automated machine.
In short
The steps at a glance
-
Pick the process
One repetitive step with steady volume, a stable part and a reason to automate it.
-
Record how it really runs
Video, drawings, sample parts, the rate at peak, the variants, and every small task the operator does.
-
Check feasibility
Grip, payload, reach and cycle time, proven with real parts and a simulation.
-
Build the business case
Labor hours, scrap and overtime from your own records, against the installed cost.
-
Write the spec and get quotes
One spec, sent to every integrator you ask.
-
Concept, design review and order
Settle the layout with the people who will run and maintain the cell.
-
Build and factory acceptance test
The finished cell runs your parts in the builder's shop before it ships.
-
Install, site test and training
Commissioned on your floor, tested again, handed to your crew.
-
Support, measure, then pick the next one
Backups, spare parts and a support plan, then compare against your baseline.
Step 1: pick the right first process
The usual rule of thumb is that robots suit jobs that are dull, dirty or dangerous. That is a fair start, but a good first project also needs steady volume and a part that stays put. Score each candidate honestly.
| Factor | Good first candidate | Fix it first, or wait |
|---|---|---|
| Repetition | The same pick, turn and place many times a shift | Different motions on every part |
| Part | One part or a small family, drawings stable | New drawings every week |
| Presentation | Parts arrive in the same place and orientation every time | Parts arrive jumbled, tangled or in a different state each time |
| Volume | Steady across shifts and seasons | A short run that ends next quarter |
| Bottleneck | The work queues in front of this step | The station already waits on the steps around it |
| Judgment | A pass or fail that a sensor or camera can check | A call a person makes by look and feel on each part |
If two candidates tie, pick the one your crew finds hardest to staff, such as heavy lifting, heat or tedious repetition. Our guide to automation for small manufacturers covers what to measure for a few weeks before you choose.
Step 2: record how the process really runs
The operator does more than the work instruction says. They flip a part that came in upside down, knock off a burr, glance at a label, set aside one that looks wrong, and wait for the machine before them. Each of those becomes a station, a sensor, a camera or a decision in the program, so they need to be on the list before anyone designs anything.
Film the whole cycle at normal speed, including where the part comes from and where it goes next. Film a changeover and a jam if you can. If cameras aren’t allowed on your floor, a sketch and a phone call cover most of it.
Gather before the first conversation
- A video of the job being done by hand, or a description and a sketch
- Part drawings or CAD models, and sample parts, including the bad ones
- The rate at your best hour, not the average, and the number of shifts
- Every part variant, and how often you change over
- How parts arrive at the station and how they leave
- The small tasks the operator does that aren't in the work instruction
- Signals or timing that depend on the machines before and after the station
Step 3: check feasibility before you buy
A feasibility check settles a handful of physical facts:
- Whether the part can be gripped without marking, slipping or dropping it.
- What the part and the gripper weigh together, and how far the robot has to reach to the farthest point.
- Whether the robot can finish a cycle in the time the line allows per part.
- How much the part’s position varies when it arrives, which decides whether a fixture is enough or the robot needs a camera to find it.
- Whether the environment calls for a washdown or food-grade robot, or protection from heat, dust or spatter.
The answers come from testing, not opinions. Gripper trials with real parts show whether a vacuum cup seals or a finger slips. We lay out and check robot paths in FANUC ROBOGUIDE, FANUC’s offline simulation software, before they run on a real robot, which shows reach, clearances and a first estimate of cycle time. Our page on offline robot programming covers what simulation can and can’t tell you.
Feasibility is also when to ask whether a robot is the right answer at all. Sometimes the fix is a fixture, a feeder or a machine built around one part. Our custom automation page covers jobs a robot doesn’t fit.
Step 4: build the business case
Simple payback is the installed cost of the equipment divided by what it saves each year after its running costs. The savings come from labor hours at your burdened rate, scrap, rework and overtime. Use your own payroll figures where you have them. For a reference point, the Bureau of Labor Statistics put total employer compensation in manufacturing at $48.62 an hour in June 2026, of which $32.50 was wages and the rest benefits.
Freed hours only count as savings if the people move to other work or the extra output gets sold. Decide which one applies before you ask for quotes. The robot ROI calculator works out payback, ROI and NPV from the numbers you type in.
If cost or know-how is the blocker, the NIST Manufacturing Extension Partnership works with small and medium-sized manufacturers through centers serving all fifty states and Puerto Rico.
Step 5: write the spec and ask for quotes
A written spec makes quotes comparable. Without one, each integrator fills the gaps with its own assumptions and prices them differently.
The spec should cover the rate and how it will be measured, the part variants and changeovers, how parts enter and leave the cell, the floor space, power and air at the spot, your plant’s PLC and HMI standard, your safety and insurance requirements, the documents you expect at handover, and what counts as passing the acceptance tests. The automation RFQ builder turns those answers into one brief you can send to every integrator.
Send the same spec to each one, then compare answers piece by piece. Our guide on how to choose a robot integrator has the questions and a scorecard.
Step 6: concept, design review and order
The integrator comes back with a concept: the robot, the gripper, the layout, how parts get in and out, where the guarding goes and where the operator stands. Review it with the people who will live with it. Operators notice when a bin will be awkward to swap, and maintenance notices when a motor can’t be reached without pulling a guard panel.
This is the cheapest point to change anything. Moving a conveyor in the model is an edit. Moving it after the frame is welded means new steel. The firm quote and the purchase order should describe the cell as reviewed.
Step 7: build and factory acceptance test
After the order, the cell is designed in detail, fabricated, wired and programmed. Long-lead parts such as the robot are ordered early. Expect questions as the build turns up details the concept didn’t settle.
The factory acceptance test (FAT) is the run-off in the builder’s shop. IEC 62381, a standard written for process-industry automation, defines factory and site acceptance tests, and the same idea carries over to a robot cell: agree in advance what gets tested where and what counts as a pass. Send production parts, including the ugly ones, and come watch the cell fault and recover. Our FAT and SAT guide has checklists for both tests.
Step 8: install, site test and training
Before install, your side of the list is usually power and air run to the spot, a floor that can take the anchors, network access if the cell reports to your systems, and a window when the line can stop. The site acceptance test then repeats the safety checks and runs live production with your utilities and the machines on either side.
Safety stays part of the job after the builder leaves. ANSI/A3 R15.06-2025, the US robot safety standard, added a third part aimed at the companies that use robot cells. Train operators and the maintenance tech who will own the cell before the integrator leaves, and have your safety professional review the risk assessment.
Step 9: support, measure, then pick the next one
Before the project closes, collect program backups for the robot, PLC and HMI, the as-built schematics and the spare-parts list. Agree on who you call when the cell faults. On cells we install, we can connect over a secure VPN for program changes and troubleshooting when the customer allows it.
Then measure again against the numbers from Step 1. Once the first cell runs steadily and your crew owns it, the next process is easier to choose and easier to sell inside the plant.
We design, fabricate, wire and program turnkey robot cells in our Fontana shop, run them off with your parts, and install them anywhere in the United States. A video of the manual process or a part drawing is enough for us to come back with a concept.
Common questions
- Which manufacturing processes are easiest to automate first?
- Steps where the same part, or a small family of parts, arrives the same way many times a shift and leaves in a known place. Palletizing cases, loading and unloading a machine, and moving parts between a conveyor and a fixture are common first projects. Jobs that need a person's judgment on every part, or parts that arrive jumbled and different each time, are harder places to start.
- How long does it take to automate a process?
- It depends on how quickly the spec and design review close, on lead times for the robot and other bought parts, on when production parts are available for testing, and on when your line can stop for install. We don't publish typical durations. Our robot integration timeline guide lists each phase and what stretches it, and the plan we send with a concept is where a real schedule starts.
- Do we need an automation engineer on staff?
- Not to buy the first cell, but you do need an owner. One person should make decisions during the project, attend the design review and run-off, and own the cell afterwards. Your maintenance team should be trained on the robot, the PLC and the safety devices before the integrator leaves, and should hold the program backups and the spare-parts list.
- Should we change the process before we automate it?
- Often, yes. Automating a step as people do it today can copy steps a machine doesn't need, such as flipping a part only to make it easier to grab by hand. It can also copy problems, like parts that arrive in a different position every time. Fix part presentation and trace any scrap problem first, then design the cell around the cleaned-up process.
- Can a process be automated without a robot?
- Yes. Some steps are better served by a fixture, a bowl feeder, a conveyor change or a custom machine built around one part. We built a custom feeder and tapping machine for an aerospace supplier with no robot in it, run by a PLC with an operator screen. A robot earns its place when the motion is complex, the parts vary within a family, or the job will change over time.
Sources
- NIST: Manufacturing Extension Partnership (MEP)
- U.S. Bureau of Labor Statistics: Employer Costs for Employee Compensation, June 2026, Table 4 (manufacturing)
- FANUC America: ROBOGUIDE robot simulation software
- The Robot Report: A3 releases full three-part national safety standard for industrial robots (ANSI/A3 R15.06-2025)
- IEC 62381:2024, Automation systems in the process industry: factory acceptance test (FAT), site acceptance test (SAT) and site integration test (SIT)