How to write an automation RFQ that integrators can quote

A clear RFQ gets you quotes for the same cell, priced on the same assumptions. A vague one gets you three different machines and no way to choose between them.

An automation RFQ is the document you send integrators so they can quote the same cell. Most of what goes wrong with robot cell quotes starts here: a rate nobody defined, a part variant nobody mentioned, a PLC brand assumed differently by each bidder. We quote FANUC cells from our shop in Fontana, CA, and this is what we wish every RFQ had in it.

In short

A good automation RFQ describes the problem, not the machine. Include a video of the job done by hand, drawings and samples of every part variant, the rate you need at peak and how it will be measured, shifts, floor space and utilities, your plant’s PLC, HMI and safety standards, the signals to nearby machines, acceptance criteria for the factory and site tests, the handover documents, training and support. Send the same RFQ to every bidder.

The fastest way to build one is our automation RFQ builder. It walks through the job, the parts, rates, space, safety, controls standards, data and schedule, runs in your browser, and prints one brief you can send to every integrator. Add your acceptance criteria and handover list from the sections below.

What to include in an automation RFQ

The table below is the outline we’d use for a robot cell. The right-hand column is why an integrator needs each item, which also tells you what happens if it’s missing.

Section What to include Why it matters
The job today A phone video of a full cycle, the steps the operator takes, and the checks they do by eye or feel The gripper, the cycle and the sensors all come from this
Parts Drawings or CAD, material, surface, where it can be held, every variant, samples including bad ones Grippers are designed around the part; each variant adds tooling and programming
Sizes and weights Largest, smallest, heaviest and lightest parts, and placement accuracy Sets the robot’s payload and reach and whether one gripper covers them all
Rate Parts per hour at your best hour, shifts, days, changeovers, coming increases Decides how many robots, and how fast everything around them must be
Space and utilities Floor space, clear height, access, slab, power, compressed air, network Sets the layout and what has to be ready before install
Safety Whether people load while the robot runs, guarding the plant requires, EHS and insurer rules Drives the guarding, safety devices and the risk assessment
Controls standards PLC brand and version, HMI, network, robot brand, panel rules such as NFPA 79 or a UL 508A listed panel The cell should match what your crew already maintains
Interfaces Machines the cell exchanges signals with, and who owns their programs Handshakes with other equipment are a common source of start-up delays
Data What the cell should count or log, and whether it reports to an ERP or MES Network and software scope, priced up front instead of added later
Acceptance What the factory test and site test must show, and what counts as a pass Without it, done means whatever happens on test day
Handover and support Documents, backups, source files, training, warranty, who you call after install What your team keeps after the integrator leaves
Schedule and terms Target date and what sets it, install window, budget range if you have one Lets bidders plan staffing and long-lead parts realistically

Who should help write the RFQ

One person should own the RFQ, but the answers come from several people. Operators know the small tasks the work instruction leaves out and which parts cause trouble. Maintenance knows the PLC platform, the spare parts already on the shelf, and where the power and air drops are. EHS knows the plant’s guarding rules and what the insurer will ask about. IT owns the network, and the ERP if the cell has to report counts. Finance knows the budget, the payback it has to meet, and when capital gets approved.

A short conversation with each of them before the RFQ goes out costs far less than a change order after the purchase order.

Attachments worth sending

  1. A phone video of at least one full cycle, plus a changeover and a jam if you can film them
  2. Part drawings or CAD models, for every variant
  3. Photos of the station and the floor space, with a dimensioned sketch
  4. Your plant's machine or controls specification, if it has one
  5. Sample parts, good and bad, offered to every bidder on the same terms

Write requirements, not a design

Say what the cell has to do, and leave how it does it to the bidders. “Move each case from the conveyor to the pallet in the stack pattern below, at this rate” lets each integrator propose a robot, a gripper and a layout. “Use a six-axis robot with a vacuum gripper” locks in a design that may not be the best one, and makes it hard to hold anyone to the result.

The exceptions are your plant standards. If maintenance stocks Allen-Bradley parts, if the plant requires a particular light curtain or guarding style, or if all your robots are FANUC, say so. Those are requirements, not design choices.

How to state the rate

Rate is easy to write in a way two bidders read differently. Pin it down:

  • Give the rate at your best hour, not the shift average, and say whether it includes changeovers and breaks.
  • Say how it will be measured at acceptance: how long the test runs, with which parts, and with the upstream and downstream equipment running or simulated.
  • List the variants and the mix, because a cell that hits rate on the easy part can miss it on the hard one.
  • Mention increases you expect in the next few years, so the cell isn’t sized for today only.

If you don’t know a number yet, say so and give a range. An open item marked as open gets a question back. A guess gets priced as if it were true, and differently by each bidder.

Put acceptance criteria in the RFQ

The factory acceptance test (FAT) happens in the integrator’s shop, and the site acceptance test (SAT) on your floor. IEC 62381, a standard for process-industry automation, defines both tests and is meant to help owners and vendors agree on test scope and responsibilities ahead of time. The same idea works for a robot cell. Write down what each test must show before anyone quotes: the rate run, every changeover, fault recovery, each safety function, and the documents delivered. Our FAT and SAT guide has checklists to copy from.

On safety, ask each bidder which edition of the robot safety standard they design to and who does the risk assessment. In the US that standard is ANSI/A3 R15.06-2025. Our robot risk assessment guide explains the method.

Common automation RFQ mistakes

Mistakes to avoid

  1. Describing a machine instead of the job, so every bid is a different machine
  2. Giving the average rate, not the peak, and not saying how it will be measured
  3. Leaving out part variants that run rarely, or sending only the good parts
  4. No plant standard for the PLC, HMI or safety devices, so each bidder assumes its own
  5. Utilities, rigging, anchoring and floor work not assigned to anyone
  6. No acceptance criteria, so the run-off has no agreed pass
  7. No handover list, so backups and source files are left to chance
  8. Different information sent to different bidders, or answers to questions shared with only one

How to compare automation quotes

When the quotes come back, compare scope before price. Put them side by side, one line per piece of the cell: design, frame and guarding, gripper, conveyors and feeders, control panel, robot program, PLC and safety logic, HMI, run-off, install, training and documentation. Mark each line as included, excluded or not mentioned. Our robot cell cost breakdown lists the lines most quotes contain.

Then read the assumptions and exclusions closely. A low quote often assumes parts arrive in a fixed position, or lists conveyors, guarding or install as by others. Check payment milestones, warranty terms, what happens if the rate isn’t met, and how long the price is valid. Options priced separately deserve their own column: a spare-parts kit, extra training days, an extended warranty, a second gripper for a future part. One bidder may have included what another listed as an option. Ask clarifying questions in writing and share the answers with every bidder. The scorecard in our guide on how to choose a robot integrator covers the questions about who builds what.

Once you have a firm number, the robot ROI calculator turns it into payback from your own labor and production figures.

Sending an RFQ to us

We design, fabricate, wire and program turnkey robot cells in Fontana, run them off in our shop and install them at plants across the US. You don’t need a finished RFQ to start. A video of the manual process or a part drawing is enough for us to come back with a concept and a plan. Send it through our contact page, or attach the brief from the RFQ builder.

Common questions

How long should an automation RFQ be?
Long enough to answer the questions an integrator would otherwise guess at, and no longer. For a single robot cell that is often a few pages plus attachments: a video of the process, part drawings, a layout sketch with the floor space, your plant's controls and safety standards, and the acceptance criteria. Our RFQ builder walks through those questions and prints them as one brief.
Should an automation RFQ include a budget?
If you have one, it helps. A budget range tells integrators whether to propose a simple cell or a more capable one, and saves a round of redesign when the first concept comes in far off. If you can't share it, say which matters more, the lowest first cost or the most flexibility for future parts, so bidders size the cell the same way.
What is the difference between a budgetary quote and a firm quote?
A budgetary quote is an estimate for capital planning, made from limited information and usually without a full concept design. A firm quote is a price to build a defined cell, normally after a concept, part trials and your review of the layout. Ask which one you are getting, how long it is valid, and which assumptions would change it.
How many integrators should we send the RFQ to?
Enough to compare, few enough that you can give each one real attention. Every bidder should get the same RFQ, the same sample parts and the same answers to questions. If one bidder's question exposes a gap in the RFQ, send the answer to all of them in writing so the quotes stay comparable.
Can we send an RFQ before we have a full spec?
Yes. A video of the job, a drawing and the rate you need are enough to start a conversation and get a concept. Mark the open items as open rather than guessing, and expect the price to firm up once they are settled. A rough RFQ that says what is unknown is more useful than a detailed one built on guesses.

Sources

  1. IEC 62381:2024, Automation systems in the process industry: factory acceptance test (FAT), site acceptance test (SAT) and site integration test (SIT)
  2. NFPA 79, Electrical Standard for Industrial Machinery
  3. UL Solutions: Industrial control panels and the UL 508A panel shop program
  4. The Robot Report: A3 releases full three-part national safety standard for industrial robots (ANSI/A3 R15.06-2025)

Start a project

Bring us the process. We'll bring the cell.

Send a phone video of the manual process, or a part drawing, by text or email. We come back with a cell concept and a plan: robot, tooling, controls and code.

Call or text
Call or text
(818) 397-4809
Email
sales@calwestmfg.com
Shop
13815 Arrow Rte, Fontana, CA 92335
Hours
Mon–Fri 7:00am – 3:45pm

FANUC Authorized System Integrator (ASI). Part of CalWest Manufacturing, founded 2012: AS9100D and ISO 9001 certified, ITAR registered.